Re: How to separate Capex & Opex WBSs

$
0
0

Hi,

One option you have at WBS element is choosing Project Type selection- as you wanted to have both CAPEX and OPEX in one project structure.

 

Ideally speaking, i will never suggest to have both types in project structure rather would like to have to two different project structures.

 

Responsible Cost Center field can be made as a mandatory feild to provide CTR information.

You can validate Project type for setting up validation.

 

Thanks,

Sudhakar