Re: Stock of component not used by CTM to do immediate partial fulfillment of demand of finished good

$
0
0

Hi Dogboy,

 

In the given example, lot size and safety stock parameters are removed in location-product masters/TLanes of FG1 and C1 to make it a simple  scenario. Thanks.

 

Hi Marius,

Option of Supply Consumption looks good for the subject issue. I missed to tell about APO version. Client is using SCM 5.0 and I do not see option of Supply Consumption in STRATEGIES tab page of CTM profile in this version.

 

 

Thanks for your advice though.

 

Apology for delay in replies to both of you.

 