Re: Weekday and Weekend Scheduling of Process Chain

$
0
0

hi,

 

as solution suggested by Raman, 7 jobs are not required.

i think only three jobs are enough.

 

cretae two jobs.

1. jon_mon_fri_6am  give options daily and restrict on don't run on sun and holidays. give start date

2. job_sat_10am give options weekly and restrict always execute job. give start date

3. job_sun_10am give options weekly and restrict always execute job. give start date.

 

 

steps to create job.

 

1. go to SM36, give your job name.

2. in start condition give start date and time

3. enter period values--weekly/daily etc..

4. give restrictins

5. i step give program to run.

 

hope this helps.

 

 

Regards

Konda Reddy